This busy waste water plant in Palmerston North needed a custom-made crane system to be designed, manufactured and installed with minimal disruption to their operation.
The original Pump Station building had been commissioned many years previous without any lifting mechanisms in place to maintain screens, pumps and motors. Maintenance on the existing equipment was due to be undertaken so a tight timeframe was of the essence.
Our installations team had to plan working around the existing machinery, a low roof clearance for some of the area to be covered and also a 6.00m dropped floor area. Being in a semi outdoor and corrosive area also brought challenges that need to be overcome.